How much will it cost?

Please note when paying for building permit or development applications, the current acceptable forms of payment are cash, check or money order.

Permit Fees

Permit Fees shall be as follows (plus a Plan Review Fee):

Valuation ScheduleFee
$1 to $500$23.50
$501 to $2,000

$23.50 for the first $500 plus $3 for each additional $100, or fraction thereof, to and including $2,000.

$2,001 to $25,000

$69.25 for the first $2,000 plus $14 for each additional $1,000, or fraction thereof, to and including $25,000.

$25,001 to $50,000

$391.25 for the first $25,000 plus $10.10 for each additional $1,000, or fraction thereof, to and including $50,000.

$50,001 to $100,000

$643.75 for the first $50,000 plus $7 for each additional $1,000, or fraction thereof, to and including $100,000.

$100,001 to $500,000

$993.75 for the first $100,000 plus $5.60 for each additional $1,000, or fraction thereof, to and including $500,000.

$500,001 to $1,000,000

$3,233.75 for the first $500,000 plus $4.75 for each additional $1,000, or fraction thereof, to and including $1,000,000.

$1,000,001 and up

$5,608.75 for the first $1,000,000 plus $3.15 for each additional $1,000, or fraction thereof.

Plan Review Fee

The Plan Review Fee shall be 65% of the building Permit Fees as shown. The plan review fees specified in this Subsection are separate and in addition to the required building permit fees. Plan review fees will be waived for one and two family dwellings.

Miscellaneous Permit Fees

Miscellaneous Permit Fees shall be as follows:

PermitFee

Certificate of Occupancy

$75

Demolition Permit

$50

Detached Accessory Building

Per Valuation schedule

Pole Inspection

$65

Duplicate Permit Card

$10

Irrigation Permit

Per Valuation schedule

Fence Permit

Per Valuation schedule

Re-inspection Fees (residential)

$47

Re-inspection Fees (commercial)

$47

Spa Permit

$100

Structural Moving Permit

$100

Swimming Pools (above-ground)

$50

Swimming Pools (in-ground)

Per Valuation schedule

Temporary Building Permit

$50

Underground Fuel Storage Tank

Per Valuation schedule

Other Inspections & Fees

InspectionFee

Inspections outside of normal business hours (minimum charge - two hours)

$47 per hour1

Re-inspection fees assessed under provisions of Section 305.8 (minimum charge - one hour)

$47 per hour1

Inspections for which no fee is specifically indicated

$47 per hour1

Additional plan review required by changes, additions or revisions to plans

$47 per hour1

For use of outside consultants for plan checking and inspections, or both

Actual costs2

  • Or the total hourly cost to the jurisdiction, whichever is the greatest. This cost shall include supervision, overhead, equipment, hourly wages and fringe benefits of the employees involved.
  • Actual costs include administrative and overhead costs.

Show All Answers

1. When is a building permit required?
2. How do I obtain a commercial permit?
3. How long does it take to get a building permit?
4. What inspections are required?
5. How much will it cost?
6. Do I need a permit for a private alarm system?