How long does it take to get a building permit?
The amount of time varies based on the complexity of the work, but generally you can expect the following time frames:
1. Residential building permits may take up to 5 working days.
2. Simple add-ons, or garage permits can be processed in one to two days.
3. Commercial building permits for new construction and remodeling could take up to 10 working days depending on the complexity.
|